Building Our Future

 

Diese Seite auf Deutsch ansehen

DEUTSCH

The journey to this day is one built on the pioneering work of past Board Chairs, Heads, Teachers, Students, and Parents. It is a journey shaped by the possibilities of what the future could hold for education at our school, and what our kind of education is.

We are pleased to share with our community, and those who wish to join it, the path for the transformation of our campus, and in so doing invite you to walk with us, into our tomorrow.

The Campus Development Project will take shape across the campus in a way that connects Stage 1A & BStage 2, and Stage 3.

 

Stage 1B

Stage 1B

Understanding the imperative of space, and in preparing our campus for the changes it would undergo, we introduced The Pavilion – Stage 1B, which was completed in December 2024.

Discover More about Stage 1B
Stage 2

Stage 2

We believe in the Creative Arts and the role it plays in the richness of our students' lives and so we introduce you to The Extension – Stage 2.

Discover More about Stage 2
 

Updates - What's Happening 

10 June - 31 August 2025: Reinforcing the Secondary Building

25 August 2025 - 28 February 2026: Fourth and Fifth floors built on the Secondary Building

February - April 2026: Interior fit-out of Extension

August 2025 - June 2026: Middle and Senior School classes take place in the Pavilion. DSC classes will continue as usual throughout the transition.

June 2026: Opening of the Extension

 


If you have any questions regarding Campus Development Project you can contact us at campusdevelopment@icsz.ch.